SINGAPORE – From end-2026, preparatory works for the reclamation of Long Island will start in two phases in the waters off East Coast Park.
The works involve the clearing of seabed obstructions and movement of materials like sand.
Altogether, the sea space covered by the works amounts to about 725ha, or nearly twice the size of Marina Bay.
The Straits Times unpacks how the park’s users and businesses will be affected.
Sea sports are not allowed within the Phase 1 work area. These include sailing, windsurfing and kayaking.
Sport Singapore said that government agencies will work with affected groups to continue their activities at alternative sites. This includes the sea space to the east of Bedok Jetty, as well as other locations like Changi, Pasir Ris, Sembawang and Sentosa.
The statutory board said waters to the east of Bedok Jetty will remain available for sea sports activities until at least 2029.
According to the Kitesurfing Association of Singapore, the sport is allowed at East Coast Park from Bedok Jetty up to Marina South – the area that will be impacted by works during phase one – during the south-west monsoon season.
The second phase of preparatory works off the east of Bedok Jetty is slated to start after the completion of major international sporting events, including the South-east Asian (SEA) Games in 2029. More details will be shared when the agencies are ready.
Fishing near the shore and at Bedok Jetty can continue.
However, the works could displace fish and reduce catch rates in the area.
Agencies will put up early communication and signs to keep anglers informed.
The preparatory works will be clearly demarcated by silt screens and floating barriers.
Swimming near the shore will be allowed, as works will take place at least 130m away from the East Coast shoreline.
Users of the sea are advised to maintain a safe distance from marine vessels deployed for work. The designated work area that will be cordoned off to ensure public safety.
Beaches, exercise paths and tracks will remain open and accessible.
An increase in visible wind-blown dust is anticipated near the project. This is not expected to cause significant discomfort or require protective measures.
The URA told ST it does not expect land-based activities to be affected by the works, but the government agencies have been offering shorter tenancy extensions to businesses at East Coast Park to provide greater flexibility during this period of works for Long Island.
It did not share how many tenants took up shorter leases.
“We will continue to engage tenants closely and support their transition plans, where necessary,” the agency added.