Proman is investing approximately TT$270 million in a major turnaround at its AUM downstream complex at Point Lisas, with more than 2,500 workers expected to be involved in the 34-day exercise.
The turnaround, which began on November 4, involves the temporary shutdown of the complex’s urea, urea ammonium nitrate (UAN) and utilities plants to facilitate extensive inspections, maintenance, repairs and equipment upgrades.
The company expects production to resume on December 9, with work currently progressing according to schedule.
During a media briefing and tour of the facility yesterday, Turnaround Manager Teressa Martinez said the exercise was critical to ensuring the plants could operate safely and reliably until their next planned turnaround in 2029.
She said the work involved more than 1,300 jobs across the three facilities, requiring approximately 1,800 people during peak daytime operations.
When night-shift workers are included, the number of people on site during peak periods is expected to reach between 2,500 and 2,700 over a 24-hour period.
More than 70 local companies have been engaged to provide services for the turnaround, with approximately 52 per cent of the overall expenditure expected to benefit the local economy.
By the end of the exercise, the company expects approximately 1.5 million man-hours to have been expended during the planning and execution phases.
Martinez said the turnaround involved several critical engineering operations, including repairs to a nitric acid storage tank which had previously been operating at only 44 per cent of its capacity because of leaks.
Restoring the integrity of the tank is a major priority, as nitric acid is one of the essential inputs used in the production of UAN fertiliser.
The company is also undertaking critical inspections and maintenance of the stripper unit in the urea plant’s ACES loop to improve its reliability.
Another significant undertaking is the replacement of a 26-tonne expander unit on the UAN plant.
Martinez said this was the first time the equipment was being replaced since the complex was commissioned in 2009, making the operation one of the major heavy-lifting exercises of the turnaround.
She explained that the three facilities were closely interconnected, requiring careful coordination to ensure that work in one area did not compromise the safe and reliable operation of the others.
The urea plant produces urea in liquid form, which is transferred to the UAN plant, where it is combined with ammonia and nitric acid to produce the fertiliser for export.
The utilities plant provides essential services, including raw water, cooling water and steam, to support production.
Martinez said the turnaround had so far recorded no major incidents or accidents, a safety record the company was seeking to maintain throughout the exercise.
She said the initial phase involved shutting down the plants, purging equipment and preparing the facilities for maintenance crews.
Workers are now carrying out major inspections and assessments, alongside specialised work requiring support from overseas technical teams, including Toyo, the process designers for the ACES loop.
The next phase will involve pre-commissioning activities, including closing equipment, final inspections, integrity checks and functional testing before the facilities are returned to operation.
Martinez said the company had also established procedures for managing waste generated during the turnaround, including metal, effluents and spent catalysts, with materials handled according to the appropriate disposal and recycling requirements.
The turnaround is expected to create opportunities for local contractors and service providers while supporting the long-term operation of the Point Lisas complex.